Example of Calculation of Budget Load
The Projected budgetis calculated from the following components:
-
Invoices that are not assigned to a PO
-
Invoices that are assigned to closed POs
-
The Value of opened POs if the assigned invoice amounts are smaller than the PO value
-
Invoices assigned to opened POs, if the invoice amounts are greater than the PO value
The following items are created for an activity:
Three invoices (€ 100, € 750, and € 1200) are not assigned to a PO.
In addition, the following invoices are assigned to the specified POs.
Assigned |
Order value |
Assigned invoices |
Calculation status |
---|---|---|---|
PO A |
€ 2500 |
€ 500 € 250 € 700 |
Closed |
PO B |
€ 1600 |
€ 900 € 1100 |
Open |
PO C |
€ 1500 |
€ 1350 |
Open |
The Projected budget value is calculated as follows:
Part |
To consider |
Total |
Name of the Order |
---|---|---|---|
Invoices that are not assigned to a PO |
€ 100 + € 750 + € 1200 = |
€ 2050 |
|
Invoices that are assigned to closed POs |
€ 500 + € 250 + € 700 = |
€ 1450 |
PO A |
The Value of opened POs if the assigned invoice amounts are smaller than the PO value |
€ 1500 |
€ 1500 |
PO C |
Invoices assigned to opened POs, if the invoice amounts are greater than the PO value |
€ 900 + € 1100 = |
€ 2000 |
PO B |
|
Projected budget: |
€ 7000 |
|